Welcome to Foshan Co., Ltd. joint willy!
PVC flooring installation complicated? What are the requirements?

PVC flooring installation complicated? What are the requirements?

First, the mobile installation:
Between the floor and the floor with a dedicated connection supporting manufacturers with adhesive into one, the floor and the floor surface is not bonded PVC sports flooring can freely be rolled or removed for easy mobility.
Second, fixed installation:
1. Semi-Fixed: double-sided tape, between the floor and the floor with double-sided tape manufacturers supporting with an adhesive into one, while the ground floor is also connected with an adhesive, it can effectively prevent the occurrence of the floor due to strenuous exercise Mobile, slotted, but also facilitate the future because there is a need to move and do the entire site.
2. Local bonding: on the ground floor as a reference to the edge of the brush 20cm inward adhesive connection.
3. The full adhesive bonding: laying on the ground in the upcoming All gluing adhesive.
[Grassroots requirements]:
Construction ground grass roots must be clean, durable and clean, flatness, and no cracks. Concrete floor moisture content must not exceed 2.5%. Gypsum ground moisture content must not exceed 0.5%. Before laying on the floor. After the floor by the dust, you can lay PVC plastic sports flooring. If the original ground may be about 2mm when construction leveling uneven. If a non-absorbent surface such as mineral grass, stone, tile, etc., directly to the pavement.
[Note]: If it is damp basement floor, ground floor waterproofing layer must be done to isolate the vapor.
【installation steps】:
1. laying ground must be smooth and clean.
2.PVC plastic sports flooring before laying must begin earlier than laying tile on the floor for 24 hours, and on-site temperature should not be below 15 ℃. After the floor reduction, cutting both ends should stay 5cm. Before pasting reverse roll up the expanded floor about halfway, then squeegee the laying of - starting from the middle - the glue with a spatula toothed construction.
3. Press the floor numbers in order, the alignment of the merger, attention to the process to align the field pavement line.
4. commissure open along two adjacent floors, dedicated connection to manufacturers supporting band on the lower side of the commissure, in connection with the gluing surface, the first of which is connected with a board stuck half, then The other half of the stick in the remaining connection belt abutting the gap can be.
5. Recommends the use of harmless water-soluble glue for construction. With soft wood from the middle to the ends of the floor surface to make it smooth extrusion floor when pasted without leaving bubbles, the most thorough rolled flat.
6. Subject to the floor slotting, welding shop after Visco, welding wire should be leveled.

Hot List
Similar articles Top
News articles
Your browsing history

20014-2020 Foshan joint Huili Flooring Co., Ltd [GuangDong ICP No. 15062873 -1]
Phone: +86 0757-81992001 / 81992002 VIP Line: 13760998988
Fax: +86 0757-66811911 E-mail: xurongmin001@yahoo.com.cn Website: www.lhfloor.com
Address: Nanhai District of Foshan City Luocun Foshan airport entrance on Union
Main products: PVC flooring | Plastic flooring | sports flooring | Rubber flooring | Stone Sculpture flooring